TDL migrates legacy Allen-Bradley PLC-5 and SLC 500 systems, their DH+, DH-485 and ControlNet networks and older HMI/SCADA to ControlLogix, CompactLogix, EtherNet/IP and FactoryTalk View. Project references cover a thermal power plant, gas facilities, a fertilizer plant, factories and offshore platforms in Vietnam.

When to plan the upgrade

Signs it is time

  • Rockwell Automation announced the discontinuance of the PLC-5 platform in June 2017: processors such as the 1785-L80B, 1785-L80E and 1785-L80C15 are discontinued since 31 July 2017, and the 1785-ENET Ethernet module since 18 May 2017.
  • Spare parts have followed: the 1771-OBD output module was discontinued on 31 January 2021, the 1771-P7 power supply on 31 March 2021 and the 1784-PKTX DH+ card on 31 March 2022.
  • SLC 500 processors such as the 1747-L532, 1747-L542 and 1747-L553 were discontinued on 31 March 2024.
  • MicroLogix 1000, 1100, 1200 and 1500 controllers are discontinued; MicroLogix 1400 is Active Mature.
  • RSLogix 5 has reached End of Life, with no more anomaly corrections or functional improvements, and new RSLogix 5 activations stopped being sold on 31 December 2025.
  • The release notes of RSLogix 5 v10 and RSLogix 500 v12 list Windows 7 and Windows 10 as supported, but not Windows 11.

Risks of waiting

  • Rockwell lists the replacement as an engineering replacement: a different controller that needs program conversion, not a drop-in spare.
  • After discontinuation, Rockwell states only that repair and exchange services may be available.
  • Remaining stock is limited and regional, and some items run out before their discontinued date.
  • Rockwell notes that spare parts, repaired units and engineers who know the PLC-5 are becoming scarce.

A phased path reduces the risk: 1756-RIO or 1747-AENTR adapters let the existing PLC-5 or SLC I/O stay in service under a new controller, and 1492 conversion systems later replace the I/O without removing the field wiring.

Source: Rockwell Automation product lifecycle pages, MIGRAT-PP003E, MIGRAT-PP004C, the RSLogix 5 end-of-life notice (28 January 2025) and RSLogix release notes, read 24 October 2026. To check your own parts, use the Product Lifecycle Status search on rockwellautomation.com, or ask TDL for a lifecycle review.

Check your PLC-5 or SLC 500 system

Six questions about the system you run. The findings use Rockwell Automation and Microsoft lifecycle dates; nothing is sent until you choose to send it.

Which controllers do you run?
Is there a spare processor on the shelf?
Programming PC operating system
Networks to the I/O or other devices
Operator screens
Next planned shutdown

What TDL delivers

Project references

ProjectYearOriginal systemUpgraded to
JVPC Rang Dong Field – RO Water Maker PLC Upgrade, SLC 500 to CompactLogix 53802025–2026SLC 5/03 with 1746 I/O · HMI on DH-485CompactLogix 5380 with 5069 I/O · existing PanelView relinked over EtherNet/IP
Phu My Fertilizer Plant – 40-PK-5001 Ammonia Compressor Control Replacement2025Allen-Bradley PLC-5Redundant ControlLogix 5580 with redundancy modules · FLEX 5000 I/O · PanelView Plus 7 Performance 12-inch HMI
Phu My Fertilizer Plant – Tripper Car Control System Upgrade2023Allen-Bradley SLC 500ControlLogix 5580 XT · Flex XT remote I/O · EtherNet/IP DLR · ControlNet fibre link
PV GAS Vung Tau Terminal (Thi Vai) – Loading Arm System HMI Replacement2023RSView32 HMI on a redundant PLC-5 systemFactoryTalk View SE · DH+ to EtherNet/IP converters · new workstations
Crown Dong Nai – Cupper Line 1 PLC-5 to ControlLogix Upgrade2023Allen-Bradley PLC-5ControlLogix 5570 · PanelView Plus 7 · PowerFlex 755 and PowerFlex 525 · resolver-based cam module · Guardmaster safety relay
JVPC N1 Wellhead Platform – Process Control System Upgrade2022Allen-Bradley PLC-5ControlLogix, FactoryTalk
CFT Copper – PLC-5 and DC Drives Upgrade for Mill, Furnace and AMPS2021Allen-Bradley PLC-5, HMI and DC drivesControlLogix · PowerFlex DC drives · FactoryTalk View
Pha Lai II Thermal Power Plant – Subsidiary Systems Migration2020Allen-Bradley PLC-5 / CitectControlLogix / FactoryTalk View SE
Vietsovpetro Central Compressor Platform – EDG and Switchgear Control System Upgrade2020SLC 5/01 (EDG panel) and SLC 5/03 (switchgear monitoring) on DH-485CompactLogix with 1769 I/O · FactoryTalk View SE local station · Modbus TCP to the platform ICSS
Phu My Gas Distribution Station – PLC-5 / HIMA to ICSS Upgrade2019Allen-Bradley PLC-5 / HIMAIntegrated Control & Safety System: redundant ControlLogix (process control) and AADvance (fire and safety system)
Dinh Co GPP – CC01 Turbo Expander Control System Upgrade2019Allen-Bradley SLC 500Redundant ControlLogix, PanelView HMI
Crown Dong Nai – Body Maker PLC-5 to CompactLogix Upgrade2017Allen-Bradley PLC-5CompactLogix · PanelView HMI · AC drives
Phu My Fertilizer Plant – Fuel Gas Control System Upgrade2017Allen-Bradley SLC 500Redundant ControlLogix with redundant I/O
Nestlé Dong Nai – Maggi Line and CIP Control System Upgrade2016Allen-Bradley SLC 500, WonderwareControlLogix · Wonderware · power control system
Dinh Co GPP – Gas Compressors K-01, K-02, K-03 Control System Replacement2016Allen-Bradley SLC 500Redundant ControlLogix · PanelView HMI
Ba Ria Gas Distribution Station – Piping Monitoring Control System Upgrade2014Allen-Bradley PLC-5 · RSView32Redundant ControlLogix · FactoryTalk View SE server and clients · EtherNet/IP DLR remote I/O

Technical articles

Frequently Asked Questions

Can the existing PLC-5 or SLC 500 I/O be kept?

Often yes. Depending on the plant, the existing I/O can stay for a first phase and be connected to the new ControlLogix controller, or be replaced with new I/O in the same panel. TDL compares both options during the survey.

How long does the plant need to stop?

The program is converted and tested before the stop, so site work is limited to installation, checks and start-up. The length depends on the I/O count and wiring; past migrations were done within planned shutdowns, including an 8-day platform shutdown.

Is the HMI migrated as well?

Yes. RSView32, Citect and PanelView applications are migrated to FactoryTalk View SE/ME and PanelView Plus 7 together with the controller.

Still running PLC-5, SLC 500 or ControlNet?

Speak directly with our engineers. Your RFQ, scope of work or drawings are answered by the engineers who program and commission the systems, from the first review of the existing system to the proposed solution.