Dinh Co GPP – CC01 Turbo Expander Control System Upgrade 2019
TDL migrated the SLC 500 control system of the CC01 turbo expander at Dinh Co Gas Processing Plant to a redundant ControlLogix platform, with Ex-p and Ex-e panels for Zone 2.
Outcome Ex-p and Ex-e panels certified for Zone 2 by a DNV (DNV GL) notified body.
Key Facts
| Facility | Dinh Co Gas Processing Plant (GPP), CC01 turbo expander |
|---|---|
| Location | Dinh Co, Vietnam |
| Industry | Oil & Gas – gas processing |
| Year | 2019 |
| Original system | Allen-Bradley SLC 500 |
| Upgraded to | Redundant ControlLogix, PanelView HMI |
| Hazardous area | Ex-p / Ex-e panels certified for Zone 2 |
Scope of Supply
- Procurement: Redundant ControlLogix system, PanelView HMI, Ex-p and Ex-e enclosures.
- Hardware engineering: Ex-p and Ex-e control and marshalling panels fabricated and certified for Zone 2 installation by a DNV (DNV GL) notified body.
- Software engineering: PLC and HMI programming, network engineering and third-party system interfacing.
- On-site services: Start-up, commissioning and hand-over at site.




Related Oil & gasPLC-5 & SLC 500 migrationControl panel engineeringEx control panels (hazardous areas)Rockwell Automation upgradesGas processing and distribution
More Projects
- 2025–2026JVPC Rang Dong Field – RO Water Maker PLC Upgrade, SLC 500 to CompactLogix 5380
- 2025Golden Pass LNG – Auxiliary Boiler Control System Commissioning
- 2024BSR – Steam Turbine Generator (STG) Network & HMI Upgrade
- 2023–2024PVEP DMDP-A Platform – Offshore Compressor Control System Upgrades
- 2023PV GAS Vung Tau Terminal (Thi Vai) – Loading Arm System HMI Replacement
- 2023FSO Rang Dong MV17 – Hi-Foam Control System Functional Test
- 2022JVPC N1 Wellhead Platform – Process Control System Upgrade
- 2021Phu My Gas Distribution Station – Heater
E-401B Controller Upgrade