Phu My Gas Distribution Station – PLC-5 / HIMA to ICSS Upgrade 2019
TDL replaced the Allen-Bradley
Key Facts
| Facility | Phu My Gas Distribution Station |
|---|---|
| Location | Phu My, Vietnam |
| Industry | Oil & Gas – gas distribution |
| Year | 2019 |
| Original system | Allen-Bradley |
| Upgraded to | Integrated Control & Safety System: redundant ControlLogix (process control) and AADvance (fire and safety system) |
Scope of Supply
- Procurement: Redundant ControlLogix system for the process control system, AADvance system for the fire and safety system, Rockwell Automation HMI software and related accessories.
- Hardware engineering: Complete replacement of the existing control panels and the engineering control desk for the ICSS.
- Software engineering: PLC and HMI programming, network engineering and third-party system interfacing.
- On-site services: Start-up, commissioning and hand-over at site.




Related Oil & gasPLC-5 & SLC 500 migrationICSS & safety systemsControl panel engineeringRockwell Automation (Allen-Bradley)GE Fanuc, Siemens and older ControlLogix migration
More Projects
- 2025–2026JVPC – RO Water Maker PLC Upgrade, Rang Dong Field
- 2025Golden Pass LNG (USA) Auxiliary Boiler Control System Commissioning
- 2024BSR Steam Turbine Generator Network & HMI Upgrade
- 2023–2024PVEP DMDP‑A Platform, Offshore Compressor Control Upgrades
- 2023PV GAS Vung Tau Terminal (Thi Vai) – Loading Arm System HMI Replacement
- 2023FSO Rang Dong MV17 – Hi-Foam Control System Functional Test
- 2022JVPC N1 Wellhead Platform – Process Control System Upgrade
- 2021Phu My Gas Distribution Station – Heater
E-401B Controller Upgrade