PV GAS Vung Tau Terminal (Thi Vai) – Loading Arm System HMI Replacement 2023
TDL replaced the RSView32 HMI of the loading arm system at PV GAS Vung Tau Terminal (Thi Vai) with FactoryTalk View SE, connecting the existing redundant
Key Facts
| End user | PetroVietnam Gas |
|---|---|
| Facility | Loading arm (LDA) system, PV GAS Vung Tau Terminal (Thi Vai) |
| Location | Ba Ria – Vung Tau, Vietnam |
| Industry | Oil & Gas – gas terminal |
| Year | 2023 |
| Original system | RSView32 HMI on a redundant |
| Upgraded to | FactoryTalk View SE · DH+ to EtherNet/IP converters · new workstations |
| TDL role | Supply, HMI conversion, network configuration, internal FAT, FAT with the customer, site SAT and |
Scope of Supply
- HMI: Conversion of the RSView32 application to FactoryTalk View SE on new operator workstations.
- Network: DH+ to EtherNet/IP converters for the existing
PLC-5 controllers; control network setup and communication with the central SCADA and other systems. - Testing: Internal FAT, FAT with the customer and site SAT.
- Commissioning: Installation, commissioning and
72-hour monitoring after cut-over.

Related Oil & gasPLC-5 & SLC 500 migrationSCADA & historianDeviceNet and ControlNet to EtherNet/IPConnecting existing equipment to SCADARockwell Automation upgrades
More Projects
- 2025–2026JVPC – RO Water Maker PLC Upgrade, Rang Dong Field
- 2025Golden Pass LNG (USA) Auxiliary Boiler Control System Commissioning
- 2024BSR Steam Turbine Generator Network & HMI Upgrade
- 2023–2024PVEP DMDP‑A Platform, Offshore Compressor Control Upgrades
- 2023FSO Rang Dong MV17 – Hi-Foam Control System Functional Test
- 2022JVPC N1 Wellhead Platform – Process Control System Upgrade
- 2021Phu My Gas Distribution Station – Heater
E-401B Controller Upgrade - 2021PV GAS Vung Tau Terminal (Thi Vai) – SC300E Shutdown System Firmware Upgrade