PV GAS Vung Tau Terminal (Thi Vai) – Loading Arm System HMI Replacement 2023

TDL replaced the RSView32 HMI of the loading arm system at PV GAS Vung Tau Terminal (Thi Vai) with FactoryTalk View SE, connecting the existing redundant PLC-5 controllers to the new HMI through DH+ to EtherNet/IP converters.

Key Facts

End userPetroVietnam Gas
FacilityLoading arm (LDA) system, PV GAS Vung Tau Terminal (Thi Vai)
LocationBa Ria – Vung Tau, Vietnam
IndustryOil & Gas – gas terminal
Year2023
Original systemRSView32 HMI on a redundant PLC-5 system
Upgraded toFactoryTalk View SE · DH+ to EtherNet/IP converters · new workstations
TDL roleSupply, HMI conversion, network configuration, internal FAT, FAT with the customer, site SAT and 72-hour monitoring