Home › Services

Automation for Offshore Platforms and FSOs

Since 2013 TDL has worked on control and safety systems offshore Vietnam: on Vietsovpetro's Central Compressor Platform and BK-20 and BK-21 wellhead platforms in the Bach Ho field and its Riserblock Central Processor Platform, on JVPC's N1 wellhead platform and a JVPC platform in the Rang Dong field, on PVEP's DMDP-A and Thang Long – Dong Do platforms, and on MODEC's FSO Rang Dong MV17. Where the projects call for it, the work is tested at FAT before going offshore and installed within planned platform shutdowns. The projects below are grouped by system.

By system

Related services

Project references

Frequently Asked Questions

Which offshore operators has TDL worked for?

Vietsovpetro, JVPC, PVEP and MODEC, from 2013 to 2026: on compressor, wellhead, processing and utilities platforms and on the FSO Rang Dong MV17.

Can a platform control upgrade fit within a planned shutdown?

On Vietsovpetro's Central Compressor Platform in 2020 the new EDG and switchgear controllers were installed 1:1 in the existing cabinets within a shutdown of up to eight days. On PVEP's DMDP-A platform the FAT was done at TDL's workshop before the offshore shutdown, and modules still in active lifecycle were kept to keep the shutdown short.

Has offshore work been witnessed by a third party?

Yes. On the LP compressor upgrade on Vietsovpetro's Central Compressor Platform in 2018, Bureau Veritas witnessed the testing and gave third-party witness certification.

Planning control system work on a platform or an FSO?

Speak directly with our engineers. Send your RFQ, scope of work or drawings: the engineers who program and commission the systems read them and reply, from the first review of the existing system to the proposed solution.

Email sales@tdl-ia.com.vn Request a site survey Hotline · Urgent breakdown support