PV GAS Vung Tau Terminal (Thi Vai) – SC300E Shutdown System Firmware Upgrade 2021
TDL upgraded the firmware of the SC300E shutdown system at PV GAS Vung Tau Terminal (Thi Vai), from review of the configuration and application to EEPROM replacement, installation of new modules and site tests with the system vendor's team.
Key Facts
| End user | PetroVietnam Gas |
|---|---|
| Facility | Shutdown (SSD) system, PV GAS Vung Tau Terminal (Thi Vai) |
| Location | Ba Ria – Vung Tau, Vietnam |
| Industry | Oil & Gas – gas terminal |
| Year | 2021 |
| System | SC300E shutdown system |
| TDL role | System review, EEPROM replacement on processor and I/O modules, installation of new modules, site tests with the system vendor, hand-over |
Scope of Supply
- Review: Study of the system configuration, log files and existing application programs.
- Hardware: Replacement of the EEPROM chips on the processor and I/O modules; field installation of new hardware modules.
- Site tests: Site tests coordinated with the system vendor's UK team.
- Commissioning: Test run and hand-over.
More Projects
- 2025–2026JVPC – RO Water Maker PLC Upgrade, Rang Dong Field
- 2025Golden Pass LNG (USA) Auxiliary Boiler Control System Commissioning
- 2024BSR Steam Turbine Generator Network & HMI Upgrade
- 2023–2024PVEP DMDP‑A Platform, Offshore Compressor Control Upgrades
- 2023PV GAS Vung Tau Terminal (Thi Vai) – Loading Arm System HMI Replacement
- 2023FSO Rang Dong MV17 – Hi-Foam Control System Functional Test
- 2022JVPC N1 Wellhead Platform – Process Control System Upgrade
- 2021Phu My Gas Distribution Station – Heater
E-401B Controller Upgrade