FSO Rang Dong MV17 – Hi-Foam Control System Functional Test 2023
On MODEC's FSO Rang Dong MV17, TDL loaded a new program into the Omron CJ1M PLC of the Hi-Foam control system and carried out the functional test and commissioning on board.
Key Facts
| Client | MODEC |
|---|---|
| Facility | FSO Rang Dong MV17, Hi-Foam control system |
| Location | Offshore Vietnam |
| Industry | Oil & Gas – offshore production |
| Year | 2023 |
| System | Omron CJ1M PLC |
| TDL role | New program download, functional test, configuration, commissioning and hand-over on board |
Scope of Supply
- Software: Download of the new program to the Omron CJ1M PLC and system configuration.
- Functional test: Functional test of the Hi-Foam control system on board the FSO.
- Commissioning: Installation, configuration, commissioning and hand-over.


Related: Oil & gas
More Projects
- 2025–2026 – JVPC – RO Water Maker PLC Upgrade, Rang Dong Field
- 2025 – Golden Pass LNG (USA) Auxiliary Boiler Control System Commissioning
- 2024 – BSR Steam Turbine Generator Network & HMI Upgrade
- 2023–2024 – PVEP DMDP‑A Platform, Offshore Compressor Control Upgrades
- 2023 – Thi Vai Terminal – Loading Arm System HMI Replacement
- 2022 – JVPC N1 Wellhead Platform – Process Control System Upgrade
- 2021 – Phu My Gas Distribution Station – Heater E-401B Controller Upgrade
- 2021 – Thi Vai Terminal – SC300E Shutdown System Firmware Upgrade