In a conventional control panel, every motor starter and push button is wired point to point to an I/O card. Rockwell Automation's EtherNet/IP In-cabinet Solution replaces much of that control wiring with one flat cable that carries power, single pair Ethernet and device position to the starters and push buttons in the panel, behind a gateway on the plant's EtherNet/IP network. Rockwell announced it in a press release dated 20 May 2025. This article, based on Rockwell's documents, explains what the system consists of, how it fits a Logix project, the limits its manuals set, and when it is worth considering.
1. The problem it addresses
Rockwell's brochure describes traditional panels as burdened with point-to-point wiring, configuration time and hard troubleshooting (
Power wiring stays: the motor circuit still runs through breaker, contactor and overload relay. What moves onto the cable is the control side: coil power, commands, status and diagnostics.
2. What the system consists of
The user manual lists the supported devices (
| Catalog number | Role |
|---|---|
| Gateway between a standard EtherNet/IP network and the In-cabinet bus; primary power source of the bus | |
| Supplemental power tap that injects extra switched power into the bus | |
| Flat media cable, 10 m, 25 m or 100 m lengths | |
| Connectors: device plug, left and right end plugs, splicer, terminator, dust cover | |
| Interface module on a non-reversing / reversing |
|
| As the -D version, plus a data port to a 140ME breaker or an E100 overload relay | |
| Interface module for a non-illuminated 22 mm 800F push button | |
| Interface module for an illuminated 800F push button or pilot light |
The manual's examples combine a 140MT or 140ME motor protection circuit breaker with a
3. One flat cable: power, data and position
The
The limits the manuals give for one bus:
- One gateway and as many as 39 more devices; the gateway counts as one of the 40 node connections (
1834-UM001C , pp. 12, 22). - At most 25 m (82 ft) from the gateway connection to the
1486-CON-T1 terminator. Both ends must be terminated; the gateway terminates its own end (p. 22). - Connectors at least 50 mm apart, with 100 mm or more recommended to leave cable slack (pp. 22, 35).
- Cable and connectors are IP20 and for in-cabinet use only, in UL 508A industrial control panels, UL 845 motor control centers and similar ordinary locations (
1834-TD001B , pp. 6, 9). - No bending along the cable's length; route it away from strong electric or magnetic fields (
1834-TD001B , p. 9), with extra insulation where it crosses a door hinge (1834-UM001C , p. 32).
Two rules matter for maintenance.
4. How it sits on EtherNet/IP and in Logix
The
In the Studio 5000 Logix Designer project, the gateway is configured first, then the devices (p. 47). Each device on the bus appears in the Controller Organizer and generates its I/O tags automatically (p. 11). Other functions the manual describes:
- Reference topology. The project stores which device should sit at which position; the gateway can warn on a device missing, inserted, changed or mismatched at a position (pp. 51–52).
- Automatic Device Configuration. Always enabled: the controller downloads the configuration to the gateway and end nodes each time it connects, which shortens device replacement (p. 19).
- Peer commands. Up to seven per device: devices act on each other's data without the controller, for example a push button starting a starter. The manual does not recommend combining CIP Security with peer-to-peer communication (pp. 14, 16).
- Diagnostics. Predictive maintenance views show remaining or elapsed life for the gateway and the devices (pp. 62–63, 94), and Logix Automatic Diagnostics, enabled by default from controller firmware revision 33, passes device diagnostics to HMIs (p. 180).
The manual's planning example shows a 5580 or 5380 controller, a Stratix 5700 switch and Studio 5000 Logix Designer v37 or later (p. 22). Firmware, Add-on Profiles and EDS files are downloaded from Rockwell's Product Compatibility and Download Center (p. 8). Its security chapter, written for IEC
5. Power budget
The gateway feeds two channels from one 24 V DC supply: network power for every interface module, and switched power for the
- Each interface module draws about 30 to 50 mA of network power; a full bus of 40 nodes needs 1.2 to 2 A.
- The gateway provides up to 96 W of hold-in and 196 W of peak power for contactor coils.
- Switched power depends on the number of contactors, their coil types (EJ and QJ are low consumption) and how many start together.
In the manual's example, 15 contactors
Temperature matters too: for a non-ventilated enclosure the technical data gives 22 °C ambient without derating and 40 °C with derating (42 °C and 60 °C open), and NP and SP current is derated above 40 °C (
6. When it is worth considering
The system fits a new panel with many small starters and operator devices of the supported families, such as a motor control panel or a small MCC on a Logix system, where control wiring is a large share of the work. Each gateway covers 25 m and 40 nodes, so a larger panel needs more gateways.
In TDL's view it is seldom worth it on an existing panel: other starters and push buttons would have to be replaced and the panel rebuilt around the flat cable, so it is better considered when a panel is replaced anyway. It is also an in-cabinet bus, not a way to reach field devices; for those, see choosing a remote I/O adapter on EtherNet/IP.
What we check first
This is TDL's practice, not a Rockwell Automation requirement.
- The device list: every starter and operator must be one the bus supports, and anything else stays hard-wired.
- Controller, firmware and Studio 5000 versions against the Product Compatibility and Download Center, and the Add-on Profiles on the engineering workstations.
- A power budget per bus: nodes, contactor coil types, starts at the same time, and whether a
1834-SUP-PWR is needed. - Cable length and position plan within 25 m and 40 nodes, connector spacing, the door hinge crossing, and the panel temperature.
- The DLR design if the gateway joins a ring, and the IP plan on the plant side.
- Safety circuits are designed on their own. The documents we read do not present the In-cabinet bus as a safety function.
- Spares, and maintenance staff who know devices are changed with the bus powered down.
How TDL approaches it
TDL designs and builds control panels with factory acceptance testing through our control panel engineering service, and designs EtherNet/IP networks on Stratix managed switches with DLR rings through our industrial networks and OT security service. For a new Logix panel, TDL can evaluate the EtherNet/IP In-cabinet Solution against a hard-wired design on the points above. Older networks are covered in DeviceNet and ControlNet to EtherNet/IP migration and DeviceNet to EtherNet/IP; ring options in DLR vs PRP.
Frequently asked questions
What is single pair Ethernet in the EtherNet/IP In-cabinet Solution?
It is the Ethernet link carried on one pair, conductors SPE+ and SPE-, of the seven-conductor
How many devices and how much cable can one gateway handle?
One
Which devices can connect to the bus?
Bulletin
Can a device be replaced while the bus is running?
No. The manual says connectors cannot be added to or removed from an active system, and modules are disconnected from power before removal, because interrupting the cable can cause unintended operation. Automatic Device Configuration then downloads the configuration to the new device.
Can the gateway sit in a DLR ring?
Yes, through its two RJ45 ports, but only as a ring participant. Another device on the ring must be the ring supervisor.
Sources
- Rockwell Automation,
1834-UM001C-EN-P , EtherNet/IP In-cabinet System User Manual, 09/2026 — pp. 8–9, 11–14, 16, 18–19, 22–29, 32, 35, 46–47, 51–52, 62–63, 94, 159, 163, 180 - Rockwell Automation,
1834-TD001B-EN-P , EtherNet/IP In-cabinet System Specifications (Technical Data), 04/2026 — pp. 3–6, 8–9, 17 - Rockwell Automation,
1834-SP001A-EN-P , EtherNet/IP In-cabinet Solution brochure, 05/2025 — p. 4 - Rockwell Automation, EtherNet/IP In-cabinet Solution, product page with catalog list
- Rockwell Automation, press release, 20 May 2025, launch of the EtherNet/IP In-cabinet Solution
Read 23 November 2026. This article paraphrases the sources and quotes them only briefly; read the current manual and technical data before designing a panel. Links open the latest edition in Rockwell's literature library; page numbers refer to the edition cited.