Dinh Co GPP – Vibration Monitoring for Gas Compressors K-1011A/B/C/D 2015
For gas compressors K-1011A/B/C/D at the Dinh Co Gas Processing Plant, TDL supplied and installed a Rockwell Automation vibration monitoring system: Allen-Bradley XM modules, vibration sensors and Emonitor software.
Key Facts
| End user | PetroVietnam Gas |
|---|---|
| Facility | Dinh Co Gas Processing Plant (GPP), gas compressors K-1011A/B/C/D |
| Location | Dinh Co, Vietnam |
| Industry | Oil & Gas – gas processing |
| Year | 2015 |
| System | Allen-Bradley XM vibration monitoring modules on DeviceNet · vibration sensors · Emonitor software |
| TDL role | Supply, installation and equipment replacement at the plant, Emonitor configuration, start-up, commissioning and hand-over |
Scope of Supply
- Procurement: Allen-Bradley XM vibration monitoring modules, vibration sensors and Rockwell Automation Emonitor software.
- Hardware engineering: Installation and equipment replacement at the plant.
- Software engineering: Emonitor software installation and configuration.
- On-site services: Start-up, commissioning and hand-over at site.

Related: Oil & gas · Vibration monitoring
More Projects
- 2025 – Golden Pass LNG (USA) Auxiliary Boiler Control System Commissioning
- 2025 – P&G Cabuyao (Philippines) 2-Lane Servo Capper Automation
- 2024–2025 – P&G Vietnam Dong An – Packing Line Control System Modernization
- 2024 – BSR Steam Turbine Generator Network & HMI Upgrade
- 2023–2024 – PVEP DMDP‑A Platform, Offshore Compressor Control Upgrades
- 2022 – Vinh Hoan FeedOne Aquafeed Factory, Process Control & SCADA
- 2022 – JVPC N1 Wellhead Platform – Process Control System Upgrade
- 2022 – Thai Binh 2 Thermal Power Plant – ESD System Consultation (Trusted)
- 2021 – Phu My Gas Distribution Station – Heater E-401B Controller Upgrade
- 2021 – CFT Copper – PLC-5 and DC Drives Upgrade for Mill, Furnace and AMPS
- 2014–2021 – P&G Vietnam Dong An – FactoryTalk Batch Process Control
- 2020 – Pha Lai II Thermal Power Plant Subsidiary Systems
- 2019 – Dinh Co GPP CC01 Turbo Expander
- 2019 – Phu My Gas Distribution Station ICSS
- 2019 – Vietsovpetro BK-20 & BK-21 Wellhead Platforms – ICSS
- 2019 – PVEP Thang Long – Dong Do Platform – ICSS Maintenance and Repair
- 2019 – Intel Vietnam – SWTP Control System
- 2018 – Vietsovpetro LP Compressor – Siemens S5 and Bently Nevada 3300 Upgrade
- 2017 – Vietsovpetro Riserblock Platform – Sieger Fire & Gas System Upgrade
- 2017 – Crown Dong Nai – Body Maker PLC-5 to CompactLogix Upgrade
- 2017 – Phu My Fertilizer Plant – Fuel Gas Control System Upgrade
- 2016 – Vietsovpetro Central Compressor Platform – SIL 3 Fire & Gas System
- 2016 – Nestlé Dong Nai – Maggi Line and CIP Control System Upgrade
- 2016 – Dinh Co GPP – Gas Compressors K-01, K-02, K-03 Control System Replacement
- 2016 – Thanh Thanh Cong Tay Ninh Sugar Plant – Bently Nevada 3300 Vibration Monitoring Replacement
- 2015 – URC Vietnam – Coffee Extractor Production Line Control System
- 2015 – Phu My Fertilizer Plant – FAM Conveyor and Libra Packing Control System Upgrade
- 2013 – Vietsovpetro Central Compressor Platform – CO2 Control System Upgrade