Dinh Co GPP – Governor Air/Fuel Control System Replacement for Gas Compressors 2017
TDL replaced the obsolete governor air/fuel control system of gas compressors
Key Facts
| End user | PetroVietnam Gas |
|---|---|
| Facility | Dinh Co Gas Processing Plant (GPP), gas compressors |
| Location | Dinh Co, Vietnam |
| Industry | Oil & Gas – gas processing |
| Year | 2017 |
| Original system | Obsolete governor air/fuel control system |
| Upgraded to | Air/fuel control integrated into the existing ControlLogix system |
| TDL role | Supply of field instruments, installation and process modification, PLC and HMI programming, third-party interfacing, commissioning |
Scope of Supply
- Procurement: Field instruments and accessories for the modification of the existing process system.
- Hardware engineering: Field instrument installation and modification of the existing process system.
- Software engineering: PLC and HMI programming, third-party system interfacing.
- On-site services: Start-up, commissioning and hand-over at site.
More Projects
- 2025–2026JVPC Rang Dong Field – RO Water Maker PLC Upgrade, SLC 500 to CompactLogix 5380
- 2025Golden Pass LNG – Auxiliary Boiler Control System Commissioning
- 2024BSR – Steam Turbine Generator (STG) Network & HMI Upgrade
- 2023–2024PVEP DMDP-A Platform – Offshore Compressor Control System Upgrades
- 2023PV GAS Vung Tau Terminal (Thi Vai) – Loading Arm System HMI Replacement
- 2023FSO Rang Dong MV17 – Hi-Foam Control System Functional Test
- 2022JVPC N1 Wellhead Platform – Process Control System Upgrade
- 2021Phu My Gas Distribution Station – Heater
E-401B Controller Upgrade