In the public references this article uses, an LNG terminal is run from one main process control system, a distributed control system (DCS), with safety systems beside it and systems from equipment vendors around it. The emergency shutdown or safety instrumented system (ESD/SIS) and the fire and gas system (F&G) are listed as systems of their own, not as parts of the DCS. Equipment such as a boiler, a gas turbine, the ship unloading system, metering and tank gauging can come as packages with their own control systems, which pass their data to the terminal DCS. This article describes those layers as vendor references and terminal operators describe them in public; the general ICSS concepts are in What is an ICSS.
1. What an LNG terminal is made of
Wikipedia describes an LNG terminal as a facility for importing or exporting LNG, with equipment for loading and unloading ships, transfer across the site, liquefaction, regasification, processing, storage, pumping, compression and metering. Export terminals liquefy natural gas, import terminals regasify LNG, and some terminals do both.
Following the LNG through an import terminal, as the Wikipedia article describes it:
| Process unit | What happens there |
|---|---|
| Jetty and loading arms | Articulated arms move LNG between ship and shore. A pier has at least two insulated lines: one for LNG, one for vapour supply or return as the vapour space in the ship's tanks changes. |
| Storage tanks | Usually double-wall tanks: an inner tank of low-temperature alloy, insulation, and an outer tank of steel or pre-stressed concrete. LNG is kept at about −162 °C. |
| Boil-off gas | Heat leaking into the tanks vaporises some LNG. The boil-off gas can go back to a ship being unloaded, be compressed into the local gas network, or be reliquefied and returned to the tanks. |
| Regasification | The liquid is pumped to the pressure of the gas transmission system, typically 70–100 bar, and warmed in heat exchangers such as submerged combustion vaporisers, intermediate fluid exchangers or waste heat from a nearby plant; final heating may use air or seawater. |
| Gas quality and send-out | The gas may be analysed and enriched with propane or diluted with nitrogen to meet the transmission specification, then metered and odorised before it enters the high-pressure system. |
An export terminal adds liquefaction. Golden Pass LNG's own operations page describes its export project in Sabine Pass, Texas, as three liquefaction trains integrated into the existing import terminal. That terminal has five 155,000 m³ full-containment LNG storage tanks, two marine berths and regasification facilities, and the export project also adds power and utility systems and interconnections to the existing facilities.
2. The terminal DCS and what public references show
Three Yokogawa project references describe the control systems of LNG import terminals, and they show one pattern: one DCS for the process, a safety system next to it, and third-party systems connected to the DCS.
| Terminal (Yokogawa reference) | Process units named | Control and safety systems named | Other systems connected |
|---|---|---|---|
| PTT LNG, Map Ta Phut, Thailand, completed 2011 | Jetty, two 160,000 m³ full-containment tanks, boil-off gas recondenser, LNG pump, regasification train, send-out station | CENTUM VP production control system, ProSafe-RS SIS, operator training system, Plant Resource Manager asset management | Modbus links bring 10 other subsystems to the CENTUM operator stations; laboratory results flow into CENTUM for reports; custody transfer data from the truck loading system is fed back to the control system |
| South Hook LNG, Milford Haven, UK, completed 2010 | Ship unloading, five 155,000 m³ tanks, duplicated regasification and send-out | CENTUM CS 3000 DCS, ProSafe-RS SIS, ESD and F&G systems, asset management, data historian, operator training simulator | The DCS and SIS are integrated with 17 sub-vendor systems; the plant information system supplies data for gas nomination and allocation |
| Adriatic LNG, offshore gravity-based structure about 15 km off Porto Levante, Italy, completed 2009 | Mooring and unloading, two 125,000 m³ tanks, regasification plant, LNG pumps and compressors, gas turbine, flare | An ICSS of CENTUM CS 3000 and ProSafe-RS, the latter listed for IPS and F&G | LNG unloading, tank gauging, pipeline monitoring, metering and gas turbine systems connected to CENTUM through a Modbus interface |
The terminal in TDL's own case below, Golden Pass LNG, runs a DeltaV DCS, as TDL's project page states. Honeywell's regasification page lists what automation coordinates in such a terminal: high-pressure pumping and pipeline send-out, vaporizer duty allocation and pressure management, with advanced process control used for boil-off gas management. DCS basics are in What is a DCS.
3. Safety systems: SIS and ESD, fire and gas
NIST SP
The LNG sources name the same layers. South Hook lists ESD and F&G systems beside the DCS and SIS. Rockwell's LNG industry page lists fire and gas detection, emergency shutdown and safety instrumented systems, and high integrity pressure protection systems (HIPPS) among its LNG capabilities. Honeywell's page lists fire and gas detection integrated with the process control system. A list of systems does not say which functions are safety instrumented functions or what SIL each needs; that comes from the terminal's hazard and risk assessment, as explained in What is SIL.
4. Package control systems
Several parts of a terminal come as systems from other vendors. In the references above, the LNG unloading system, tank gauging, metering, pipeline monitoring and the gas turbine at Adriatic LNG were third-party systems; South Hook counts 17 sub-vendor systems; and at PTT LNG the jetty substation, laboratory, fire station and truck loading administration room are integrated with the DCS. Rockwell's LNG page adds pump, compressor and turbomachinery control with condition monitoring, and motor control and power distribution. Machine monitoring for compressors and turbines is covered in vibration monitoring.
A boiler package can include its own burner management system (BMS). Rockwell's BMS library manual (
5. How packages connect to the terminal DCS
In the PTT LNG and Adriatic LNG references, the link between these systems and the DCS is Modbus. On DeltaV, Emerson's data sheet for the Ethernet I/O Card (EIOC, December 2022) describes a card that brings data from Ethernet devices such as PLCs, motor control centers, drives and switchgear into the DeltaV system. It lists Modbus TCP, EtherNet/IP, IEC 61850 MMS, an OPC UA client and EtherNet/IP Control Tag Integration. A second EIOC on the dual carrier makes the card redundant, and the card also implements the Parallel Redundancy Protocol (PRP).
For each link, the ICSS article lists what an owner should specify: protocol, data direction, tag list, update rate, and a common time source for event time stamps. Network redundancy options are compared in DLR vs PRP.
6. TDL at Golden Pass LNG
At the Golden Pass LNG export terminal in Sabine Pass, Texas (2025), a single TDL engineer commissioned the auxiliary boiler control system on site, working for the boiler package vendor. The boiler control runs on redundant ControlLogix controllers with 1715 redundant I/O, on a PRP network architecture, and is integrated with the terminal's DeltaV distributed control system. The work covered functional testing of the BMS/SIS for SIL 2 safety functions, HMI deployment and start-up support through to hand-over. See the project page.
Closer to home, at PV GAS Vung Tau Terminal (Thi Vai), a gas terminal, TDL replaced the RSView32 HMI of the loading arm system with FactoryTalk View SE in 2023, connecting the existing redundant
What we check first
This is TDL's practice, not a Rockwell Automation or Emerson requirement. Before we commission or change a package that connects to a terminal DCS, we check:
- the interface list agreed with the DCS side: protocol, which end polls, tag list, data direction, update rate and what each side does when the link is lost;
- which trips between the package and the terminal ESD or F&G are hardwired and which go over the network, as the design documents show;
- the cause and effect matrix and the safety requirements specification for the package's safety functions, with the SIL each function needs as written there; how they are tested is in cause and effect matrix and SIS testing;
- on a PRP network, that both LANs stay separate end to end and that every device is connected as the network drawings show;
- one time source for event time stamps in the package and in the DCS;
- controller and I/O switchover tests before the loop checks with the DCS; our ControlLogix redundancy checklist lists them;
- the terminal's permit and test procedures before any trip test on site.
Frequently asked questions
Which control systems does an LNG terminal have?
A main process control system, usually a DCS; safety systems such as the SIS or ESD and the fire and gas system; and package control systems for equipment such as a boiler, a gas turbine, ship unloading, metering and tank gauging. The public references from Yokogawa show this pattern at three LNG import terminals.
Is the fire and gas system part of the DCS?
Not in the references cited. South Hook lists its ESD and F&G systems beside the DCS and SIS, and NIST lists fire and gas systems as a type of safety system, next to emergency shutdown.
How does a package PLC talk to the terminal DCS?
Over a data link such as Modbus, which the PTT LNG and Adriatic LNG references name. On DeltaV, Emerson's Ethernet I/O Card lists Modbus TCP, EtherNet/IP, IEC 61850 MMS and an OPC UA client.
What does a boiler burner management system do?
It handles flame safety. Rockwell's BMS library, for example, monitors air flow and times the purge, manages pilot and main fuel ignition and flame proving, and monitors the fuel interlocks with a safety trip and first-out capture.
What did TDL do at Golden Pass LNG?
A TDL engineer commissioned the auxiliary boiler control system on site for the boiler package vendor: redundant ControlLogix with 1715 redundant I/O, a PRP network, integration with the terminal's DeltaV DCS, and functional testing of the BMS/SIS for SIL 2 safety functions.
Sources
- Wikipedia, Liquefied natural gas terminal
- Golden Pass LNG, Operations, export project
- Yokogawa, DCS, SIS, PRM, FOUNDATION fieldbus instruments, and OTS Installed at Thailand's First LNG Terminal, project reference
- Yokogawa, Yokogawa Provides CENTUM CS 3000 and ProSafe-RS for the Largest LNG Terminal in Europe, project reference
- Yokogawa, World's First Offshore Regasification Terminal Relies on Yokogawa ICSS (CENTUM CS 3000, ProSafe-RS), project reference
- Honeywell, LNG Regasification and Import Terminal
- Rockwell Automation, Liquefied Natural Gas, industry page
- Rockwell Automation,
BMS-RM001A-EN-P , Burner Management Suite Library Reference Manual, 05/2025 — p. 13, 14, 15 - Emerson, Ethernet I/O Card (EIOC), DeltaV product data sheet, 12/2022
- NIST, SP
800-82r3 , Guide to Operational Technology (OT) Security, 09/2023 — section 2.3.7, p. 25
Read 15 November 2026. This article paraphrases the sources and does not quote them; read the original documents before designing or working on a system. Links open the latest edition in Rockwell's literature library; page numbers refer to the edition cited.