TDL Industrial Automation · Last updated:

From Rockwell's AADvance and Trusted manuals and data documents: the 20-year useful life of AADvance products, the 20-year mission time assumed in the AADvance and Trusted data, what a proof test is, why PFDavg no longer applies after the useful life (exida), the separate useful life of sensors and valves, and how to build a register, plan replacement and keep records.

A safety instrumented system (SIS) spends most of its life waiting: the valves stay open and the plant runs for years without a demand. That makes it tempting to run SIS hardware until it fails, as is sometimes argued for the basic process control system (BPCS). The vendor data used to verify a safety function is valid only for a stated useful life and mission time, and the proof test interval is a third number. This article sets out what Rockwell's AADvance and Trusted documents say about each, why the data stops applying after the useful life, and how to plan replacement. See also What is SIL and Cause and effect matrix and SIS testing.

1. Useful life, mission time and proof test interval

  • Useful life belongs to the product. The AADvance safety manual states that AADvance products have a useful lifetime of 20 years (ICSTT-RM446S, p. 16).
  • Mission time belongs to the safety function. The same manual defines it as the time that the safety instrumented function (SIF) is designed to be operational (p. 103); the AADvance PFH and PFDavg data manual gives the same definition (ICSTT-RM449J, p. 4).
  • Proof test is a periodic test that finds dangerous hidden faults, so that a repair can bring the system back to an "as new" condition or as close to it as practical (ICSTT-RM446S, p. 104).

The AADvance glossary entry for proof test ties the three together. AADvance product data is given for a useful life of 20 years; for a mission time of up to 20 years, proof testing is not required; for mission times longer than 20 years, any products still in service when that time is reached should be replaced (ICSTT-RM446S, p. 104). The same text is in ICSTT-RM448N (p. 155), ICSTT-RM458D (p. 236) and ICSTT-RM406J (p. 90). It covers the AADvance products, not the sensors and valves of the loop. Nor does it remove the periodic testing that the same documents ask for: the AADvance safety manual requires the operation and maintenance plan to include procedures for testing the system periodically, with the maximum intervals between tests (ICSTT-RM446S, p. 28), and the maintenance manual requires planned maintenance tests of the elements that internal diagnostics do not cover (ICSTT-RM406J, p. 72; see section 3). The SIS testing article cites the first of these; the two statements apply together.

The data documents state their assumptions. The AADvance data manual (system release 2.11, Eurocard release 1.41) gives its data for a 24-hour mean time to repair (MTTR) and a 20-year mission time (ICSTT-RM449J, pp. 4, 9). The Trusted TMR data document gives its tables for a 24-hour MTTR and a 20-year manual test interval (MTI), and states that the mission time is equal to the MTI and is assumed to be 20 years (ICSTT-TD002M, pp. 5–6). Both assume an ambient temperature of 40 °C and warn that a higher ambient is likely to worsen failure rates (ICSTT-RM449J, p. 9; ICSTT-TD002M, p. 5). The Trusted safety manual we read states no useful life in years.

2. Why the data stops applying after the useful life

SIF calculations assume that the failure rate of each device stays constant. In a July 2026 exida blog post, Dr Steve Gandy explains that this holds only on the flat part of the bathtub curve; in the wear-out phase it does not, and in his words, "once the useful life is exceeded, however, then the PFDavg is not applicable". The post concludes that the SIL of the SIF is then no longer valid, and notes that the manufacturer's safety manual states the useful life so that end users can plan change-outs.

The post also explains why run-to-fail is riskier in a SIS. BPCS instruments and valves are exercised all the time, so failures show up in operation. A SIS is mostly static, and idle mechanical devices can develop stiction, cold-welding and corrosion that stop the SIS from acting.

The AADvance maintenance manual also highly recommends that planned maintenance tests run at an interval shorter than the proof test interval used to calculate the PFD values (ICSTT-RM406J, p. 72).

3. Logic solver, sensors and final elements

The AADvance and Trusted data covers the logic solver: processors and I/O modules, and for AADvance the base units and termination assemblies (ICSTT-RM449J, p. 9). It says nothing about the transmitter, the solenoid valve or the shutdown valve; each has its own useful life and proof test requirements in its own manufacturer's safety manual.

The Trusted manual lists elements that internal diagnostics may not test: the final passive elements of some I/O module types, the field termination assemblies (FTAs) that interface with the sensors, the actuators themselves and the field wiring. It asks for planned maintenance testing of these, with a maximum interval set during design and highly recommended to be less than 12 months (ICSTT-RM459K, p. 27). The AADvance maintenance manual gives a similar list (ICSTT-RM406J, p. 72).

Useful life of the logic solver and of a field deviceTwo time bars on one axis in years, taken from two different Rockwell documents, for illustration only. Bar A: AADvance products, product data given for a useful life of 20 years; for a mission time of up to 20 years no proof test is required for the AADvance products; at 20 years, products still in service are replaced (ICSTT-RM446S pp. 16, 104). Bar B: the solenoid valve in a Rockwell example, useful life eleven years; the field hardware in the example needs a proof test every year; at year 11 the valve is replaced and the new valve is proof tested every year (SAFETY-AT148A p. 4). Band at the bottom: proof tests find dangerous hidden faults inside the useful life and do not move its end; this is TDL's reading.Useful life of the logic solver and of a field deviceA · Logic solver: AADvance productsProduct data for a useful life of 20 yearsmission time up to 20 years: no proof test required for the AADvance productsReplaceB · Field device: solenoid valve in a Rockwell exampleFirst valve: useful life 11 yearsReplacement valve20 yearsinstalled11 yearsproof test every year for the field hardware in the exampleTDL's readingProof tests find dangerous hidden faults inside the useful life. They do not move its end.Bar A: ICSTT-RM446S pp. 16, 104. Bar B: SAFETY-AT148A p. 4 (an example with a GuardLogix controller). Twodocuments drawn on one time axis for illustration, not one project. Read 22 November 2026. Figure: drawnby TDL.
Figure 1: Useful life of the logic solver and of a field device. On a phone, swipe sideways to see the whole figure.

A Rockwell application technique for high-pressure monitoring shows how a short field device life drives the design. The useful lifetime of the solenoid valve in that example (model 3963) is eleven years. PFD values for ten-year proof test intervals were therefore used for the logic hardware, while the sensor and final element hardware provide PFD values that need one-year proof test intervals (SAFETY-AT148A, p. 4; repeated on p. 19). The example uses a GuardLogix controller, not AADvance or Trusted; it is cited here only for the field device point.

4. What a plant can do

Both manuals put field device replacement in the maintenance plan. The AADvance operation and maintenance plan must include recalibration, testing and replacement of field devices, and the calibration of each analogue input module is measured every two years, each digital input module every five years (ICSTT-RM406J, p. 72); the same manual's calibration section recommends a drift test of digital inputs every two years (p. 21). The Trusted manual expects the same during the system lifetime, with facilities for it in the design (ICSTT-RM459K, p. 27).

A practical way to use this:

  1. Build a register of every SIS item per SIF (logic solver modules, transmitters, solenoid valves, actuators, valves) with its installation date and the useful life in its safety manual.
  2. Compare with the mission time in the SIF verification. An item whose useful life ends first is replaced before the mission time ends.
  3. Plan replacement in a planned shutdown, with the proof tests due at the same time. Lifecycle status is a separate question: a module can still be on sale and be past its useful life. Our obsolescence and lifecycle review records what is installed and its lifecycle status; see also AADvance vs Trusted. Replacing a module while the plant runs is covered in Maintaining AADvance and Trusted while running.
  4. Keep records. To meet the safety objectives through the system lifetime, the AADvance maintenance manual asks the end user and the system integrator to record all faults, failures and anomalies, with module types, serial numbers, circumstances and resolution (ICSTT-RM406J, p. 73).
  5. Watch the temperature. The Trusted manual highly recommends a temperature alarm (ICSTT-RM459K, p. 73); the AADvance manual warns that modules run continuously at the extremes of the temperature band can have reduced reliability (ICSTT-RM446S, p. 87).

Our yearly maintenance contracts cover scheduled visits with a report after each, and backups compared with the last baseline.

What we check first

This is TDL's practice, not a requirement of Rockwell Automation or of the standard.

  • The SIL target and mission time of each SIF come from the plant's risk assessment and safety requirements specification. We work to them; we do not set them.
  • We ask for the installation date of each SIS item and the useful life printed in its own safety manual, and list the earliest end date per SIF.
  • We read the assumptions behind the SIF verification data (mission time, test interval, repair time, ambient temperature) and compare them with the site.
  • Our reading of the sources: a proof test finds dangerous hidden faults inside the useful life; it does not extend the useful life. An item past its useful life is planned for replacement, not given a longer test interval.
  • We check that fault and failure records exist, with serial numbers.
  • We check the lifecycle status of each catalog number separately, before quoting spares or planning the replacement.

How TDL approaches it

TDL builds SIS for SIL 2 and SIL 3 functions on AADvance and Trusted, including ESD and Fire & Gas, through our ICSS and safety systems service. On Vietsovpetro's Central Compressor Platform, TDL supplied the main materials, including the AADvance PLC, and engineering consulting for a SIL 3 fire and gas system. On the Vietsovpetro Riserblock platform, TDL supplied and engineered the upgrade of a Sieger fire and gas system to an AADvance safety system with new detectors and control panels. At Thai Binh 2 Thermal Power Plant, TDL provided technical consultation for the ESD system on Trusted, including field operation and testing according to the SAT documents.

Frequently asked questions

What is the difference between useful life and mission time?

Useful life belongs to the product: the AADvance safety manual states 20 years for AADvance products. Mission time belongs to the safety function: it is the time the SIF is designed to be operational. The AADvance and Trusted data documents publish their figures for a 20-year mission time.

Does proof testing extend the useful life of a SIS device?

Proof testing finds dangerous hidden faults so they can be repaired. The AADvance documents say that products still in service when a mission time longer than 20 years is reached should be replaced. Our reading is that proof testing works inside the useful life and does not extend it.

Do AADvance controller modules need proof testing?

The AADvance glossary says that, with product data given for a useful life of 20 years, proof testing is not required for a mission time of up to 20 years. The sensors, actuators and field wiring of the same loop are outside that statement and need their own tests and replacement plan. The same AADvance manuals still require periodic testing in the operation and maintenance plan, and planned maintenance tests of what the internal diagnostics do not cover.

Where do I find the useful life of a transmitter or solenoid valve?

In that device's safety manual from its own manufacturer; Rockwell's logic solver data does not cover field devices. In one Rockwell example, a solenoid valve with an eleven-year useful life is the reason PFD values for a ten-year proof test interval were used for the controller hardware.

Is end of useful life the same as end of life of the product?

No. Useful life is the period for which the reliability data applies to the installed device. Lifecycle status says whether the manufacturer still sells and supports the catalog number. Both are checked, separately.

Sources

Read 22 November 2026. This article paraphrases the sources and quotes them only briefly; read the original documents before designing or working on a system. Links open the latest edition in Rockwell's literature library; page numbers refer to the edition cited.