One framework, two documents
ANSI/
When IEC 62682 first appeared, exida listed the differences from the 2009 ISA text. Many recommendations became requirements, and alarm shelving became a capability the control system supplier must provide. The recommended deadband values, latching in the state diagram and some performance metrics were removed. The lifecycle stayed the same.
ISA's
This article covers alarm management in depth. For how
What counts as an alarm
The standard defines an alarm as an audible and/or visible indication to the operator of an equipment malfunction, process deviation or abnormal condition that requires a response. Rockwell's rationalization white paper turns this into four tests:
- the condition is abnormal and needs operator action;
- ignoring it has a real consequence;
- the operator has enough time to act;
- the alarm is unique and points to the root cause.
These four tests expand the three conditions often used as a short rule — an abnormality, a required operator action and enough time to act — by adding that the alarm must be unique. A signal that fails a test is not an alarm. Record why, and keep it as an event or a notification if it is still useful. In Rockwell's paper, candidate alarms come from hazard identification and LOPA reviews, incident investigations, licensor recommendations and the existing alarm database.
The lifecycle, stage by stage
| Stage | What it produces |
|---|---|
| A Philosophy | Site rules: alarm classes, priority matrix, use of colour, change control, performance targets, roles |
| B Identification | List of candidate alarms |
| C Rationalization | Keep-or-remove decision; cause, consequence, action, response time, priority, class |
| D Detailed design | Limits, deadbands, delays, HMI presentation, state-based or advanced alarming |
| E Implementation | Installed alarms, initial tests, operator training |
| F Operation | Operators responding to alarms; refresher training |
| G Maintenance | Repair, replacement, periodic tests; alarms taken out of service and returned |
| H Monitoring and assessment | Measured performance compared with the targets |
| I Management of change | Authorised additions, modifications and deletions |
| J Audit | Periodic check that work practices follow the philosophy |
A new system starts at the philosophy. An existing system usually starts at monitoring and assessment, and an audit is the third entry point.
Siemens describes the later stages as continuous work, not a one-off project. Monitoring compares performance with the KPIs and finds bad actors to fix. Changes are reviewed and approved before implementation, and the master alarm database is updated. Periodic audits compare operation with the philosophy, and the philosophy is revised with the findings. Rockwell adds that an audit can find improvements for any stage.
Alarm classes group alarms with similar characteristics. Rockwell notes that
Rationalization: deciding and documenting each alarm
Rockwell's white paper lists nine steps: check validity; determine the consequence of inaction; document cause, confirmation and corrective action; document response time; assign priority; classify; set the limit; set the other attributes; and decide on special handling. The first four steps are knock-out tests — an alarm that fails them is removed.
- Consequence is the direct, immediate result of no response, not a chain of further failures.
- Corrective action must be something the operator does. Acknowledging the alarm does not count.
- Time to respond runs from the alarm to the last moment an action can still prevent the consequence. If that is too short for the operator to confirm and act, use automation such as an interlock instead of an alarm.
- Priority comes from severity and time to respond, looked up in the philosophy's matrix. Rockwell's example grades severity for personnel, environment and financial loss, with urgency bands of more than 30, 15–30, 5–15 and less than 5 minutes. Use no more than three or four priority levels.
- Limits should not be default percentages of range such as 10, 20, 80 and 90 % (Siemens), or other simple percent-of-range rules (Emerson/exida). Leave time to respond; Rockwell suggests using process history to see where normal operation ends.
Each result goes into the master alarm database: the authorised list of rationalized alarms and their attributes. For planning, an Emerson/exida article puts a review team's pace at about 100–200 alarms per day.
Alarm states, shelving and suppression
Siemens' summary of
| Aspect | Shelved | Suppressed by design | Out of service |
|---|---|---|---|
| Set by | Operator | Logic, from plant or equipment state | Usually maintenance, manually |
| Example | Nuisance alarm hidden during an upset | Low-flow alarm while its pump is tripped | Instrument under repair |
| Control | Returns after a set time; list of shelved alarms | Designed and documented | Listed; reviewed before return to service |
Floods, chattering and stale alarms
- Alarm flood. EEMUA 191 treats a flood as starting when a
10-minute period has more than 10 new alarms. It ends at the first10-minute period with fewer than 5. Many sources simply count10-minute periods with more than 10 alarms. VanCamp reports that badly performing systems can see more than 250 alarms in one10-minute period. Rockwell lists alarm flood suppression and state-based alarming among the special-handling options decided during rationalization. - Chattering and fleeting alarms go in and out of alarm repeatedly within a short time. Criteria vary; VanCamp gives the most common one as three or more activations within one minute. The fix is deadband and on/off delays. Siemens gives starting values: flow 5 % and 15 s, level 5 % and 60 s, pressure 2 % and 15 s, temperature 1 % and 60 s. IEC 62682 deliberately left such values out, so treat them as starting points only.
- Stale alarms stay active for more than 24 hours. Siemens notes that in many control rooms more than half of the standing alarms are for motors that are simply not running. This is where state-based alarming helps.
Performance metrics and where the numbers come from
The figures are per operator position, measured over at least 30 days (Siemens). Sources differ. Yokogawa's summary of
| Metric | Commonly cited level | Source |
|---|---|---|
| Average rate | ~1 per 10 min (~150/day) very likely acceptable; ~2 per 10 min (~300/day) maximum manageable | Yokogawa, Siemens |
| Normal operation; after a major upset | below 1 per 10 min; fewer than 10 in the first 10 min | EEMUA 191, via ABB |
| Time in flood | below 1 % (action limit above 5 %) | Siemens, VanCamp |
| Top 10 alarms, share of total | below 1 % to about 5 % (action above 20 %) | Siemens, VanCamp |
| Chattering alarms; stale alarms | zero; fewer than 5 per day | Siemens, VanCamp |
| Priorities, three levels | about 80 % low, 15 % medium, 5 % high | Siemens ( |
The chart shows why one average is not enough. A single upset pushes the shift average above 2 per 10 minutes, even though the rest of the shift is quiet. It also shows that the two flood definitions give different numbers: 3 windows have more than 10 alarms, but by the EEMUA start/end rule the flood lasts 5 windows, until the count drops below 5. State which definition a report uses. Report the average, flood time and bad actors together. A few sources usually dominate. Rockwell says bad actors can account for up to 80 % of the alarm load, and Siemens that up to 80 % of alarms may come from 10–20 tags.
Applying it during a DCS or SCADA upgrade
The alarm configuration has to be rebuilt during an upgrade anyway, so it is the cheapest moment to apply the lifecycle.
- Export the old alarm configuration — tag, condition, limit, priority, enabled state — into a spreadsheet. This is the first draft of the master alarm database. Siemens notes that one analog point can carry six or more alarms, many of them defaults.
- Pull at least 30 days of alarm history from the old alarm log or historian. Calculate the baseline: alarms per 10 minutes per console, time in flood, top 10 bad actors, chattering and stale alarms.
- Write or update the alarm philosophy before configuring the new system.
- Rationalize with operations, process and safety engineers. Emerson/exida suggest the bad actors as the starting point. Fixing them gives quick relief, but each fix should still go through rationalization, and the rest of the list still needs review.
- Import limits and priorities from the database instead of retyping them. Check the configuration against the database at FAT.
- Include packaged units. IEC 62682 covers alarms from packaged systems, and ISA has a technical report on them (
ISA-TR18.2.7 ). On EPC projects, put the alarm philosophy into package specifications at the design stage. Do the same for safety-system alarms in an ICSS. - After go-live, schedule a KPI report from the alarm log or historian. Send every alarm change through management of change, and plan periodic audits. Siemens recommends periodically comparing the running configuration with the master alarm database to catch unauthorised changes.
For the wider picture of SCADA layers, see What is SCADA.
Frequently asked questions
What is the difference between ISA-18.2 and IEC 62682?
IEC 62682 was developed from ANSI/
What are the stages of the ISA-18.2 alarm management lifecycle?
There are ten: philosophy, identification, rationalization, detailed design, implementation, operation, maintenance, monitoring and assessment, management of change, and audit. A new system starts at the philosophy, an existing system usually at monitoring and assessment.
What is documented during alarm rationalization?
For each alarm: the cause, how to confirm it, the consequence of no response, the corrective action, the time available to respond, the priority, the class, the limit and attributes such as deadband and delays. The results go into the master alarm database.
How many alarms count as an alarm flood?
EEMUA 191 treats a flood as starting when a
What is the difference between shelving, suppressed by design and out of service?
Shelving is set by the operator to hide an alarm temporarily, and the alarm returns after a set time. Suppression by design is logic based on plant or equipment state. Out of service is usually set manually for maintenance, and the alarm is reviewed before it is returned to service.
Sources
- Rockwell Automation,
PROCES-WP015B-EN-P , Alarm Rationalization and Implementation, 06/2017 - ISA,
ISA-18 Series of Standards - IEC, IEC 62682:2022 Management of alarm systems for the process industries, 12/2022
- exida, T. Stauffer, Alarm management goes global with the release of IEC 62682, 11/2014
- Yokogawa (Control Engineering), M. Tennant, Implementing alarm management per the ANSI/
ISA-18.2 standard, 2013 - Siemens (Process Online), Improving alarm management with
ISA-18.2 : Part 1, 02/2014 - Siemens (Process Online), Improving alarm management with
ISA-18.2 : Part 2, 03/2014 - Emerson (Chemical Engineering), K. VanCamp, Alarm management by the numbers, 03/2016
- Emerson and exida (Chemical Processing), T. Stauffer, K. VanCamp, Make some alarming moves, 04/2012
- ABB, Alarm management for SCADA control rooms (white paper)
- OPC Foundation, OPC UA Part 9: Alarms and Conditions, 4.8 Alarms
Read 1 November 2026. This article paraphrases the sources and does not quote them; read the original documents before designing or working on a system.