Why do it during the upgrade
When replacing a SCADA system — FactoryTalk View SE, AVEVA System Platform, InTouch or Ignition — most of the time usually goes into "redrawing it to look like the old screens". The result is a new system running on new software that keeps all the weaknesses of the old one: screens copied from P&IDs, bright colours everywhere, hundreds of alarms per shift that operators have grown used to acknowledging without a second look.
The upgrade is the only point at which fixing these things costs almost nothing extra: the screens and the alarm list have to be redone anyway. The two standards for an orderly approach are ANSI/
ISA-101 : documents before displays
On an upgrade, these documents are usually missing or out of date. Writing the philosophy and style guide and building the toolkit before the first production display is cheaper than fixing displays after FAT. The display hierarchy, the high-performance design principles and the colour budget are explained in
Habits worth leaving behind
| Common on old screens | Replace with |
|---|---|
| Copy the P&ID and put numbers on it | Layout based on the operator's tasks |
| 3D equipment, bright colours | Flat equipment, neutral colours; colour only when something is abnormal |
| Green/red for running/stopped | State shown as text; bright colours reserved for alarms |
| A number standing on its own | Value shown next to its normal operating range, with a trend where a decision has to be made |
| Pop-ups on top of pop-ups | Navigation following the display hierarchy |
| Each engineer with their own symbol style | Only symbols and faceplates from the toolkit |
The principle behind the table: a neutral background so the normal state looks quiet and abnormal conditions stand out; strong colours reserved for abnormal conditions; colour never the only way to tell states apart — always add shape or text.
ISA-18.2 : alarm only when the operator must act
Rockwell's alarm rationalization guide uses a short rule: a signal is an alarm only when there is an abnormality, the operator must do something, and there is still enough time for that action to work. If one of these is missing, it is an event, a status or a log entry, not an alarm. On an upgrade, applying this rule to the old alarm list is usually the fastest way to remove nuisance alarms.
Every alarm that is kept is rationalized and recorded: cause, consequence if nobody responds, the corrective action, the time available to respond, a priority taken from the matrix in the plant's alarm philosophy, the setpoint and the class. Yokogawa's summary of
Where the two standards meet
- A colour used for an alarm priority is not used for anything else on any display.
- Priority is shown with colour, shape and a text symbol together, so it can still be read by colour-blind operators.
- The alarm indication sits next to the item that caused it, not only in the alarm list.
- Acknowledge, shelve and jump to the alarm source work the same way on every display.
- For Logix + FactoryTalk View SE systems: fix in the style guide how controller alarm severity maps to the displayed priority, before the first alarm is configured.
Applying it in an upgrade project
- Survey: number of displays, number of alarms, and alarm statistics for at least a few weeks if the old system logs them.
- Write (or update) the HMI philosophy and style guide, and build the toolkit on the new platform.
- Rationalize the alarm list together with operations and process engineering.
- Build the displays following the hierarchy, run FAT against the style guide, and run in parallel with the old system before cutover.
- Hand over the baseline (project, alarm list, style guide) and put every later change through management of change.
How far
Frequently asked questions
Why redo the HMI and alarms during a SCADA upgrade?
Because the displays and the alarm list have to be rebuilt on the new platform anyway, fixing old weaknesses at that point costs almost nothing extra. Copying the old screens one-for-one carries every old habit onto the new system.
Which HMI documents should exist before the new displays are drawn?
An HMI philosophy with the guiding principles, a style guide that applies them, and a toolkit of symbols and faceplates built on the new platform. Writing them before the first production display is cheaper than fixing displays after FAT.
Which habits on old screens should be left behind?
Displays copied from P&IDs, 3D equipment and bright colours, green and red for running and stopped, bare numbers without their normal range, pop-ups on top of pop-ups and symbols that differ from engineer to engineer.
When is a signal an alarm?
When there is an abnormality, the operator must do something, and there is still enough time for that action to work. If one of these is missing, it is an event, a status or a log entry, not an alarm.
How many alarms per day are acceptable?
Yokogawa's summary of
Sources
- Rockwell Automation,
PROCES-WP023A-EN-P , Process HMI Style Guide, 05/2019 - Rockwell Automation,
PROCES-WP015B-EN-P , Alarm Rationalization and Implementation, 06/2017 - Yokogawa (Control Engineering), M. Tennant, Implementing alarm management per the ANSI/
ISA-18.2 standard, 2013 - ISA,
ISA-101.01-2015 , Human Machine Interfaces for Process Automation Systems — title and edition; ISA,ISA-101 Series of Standards — lifecycle scope - ISA,
ISA-18 Series of Standards — title and edition
Read 1 November 2026. This article paraphrases the sources and does not quote them; read the original documents before designing or working on a system.